Process
How a ceiling package runs, from BOQ to handover
A FUTURE ceiling package runs in five stages: BOQ review and quotation, shop drawings, samples and mock-up, installation, then snagging and handover. Each stage ends with something you approve, so problems surface on paper instead of on the ceiling.
01
What happens at each stage
| Stage | What you send us | What you get back | Your approval |
|---|---|---|---|
| 1. BOQ review and quotation | BOQ, ceiling and partition drawings, specification, target programme | Itemised quotation, list of clarifications and assumptions, proposed installation programme | Award |
| 2. Shop drawings | Approved architectural, MEP and lighting layouts | Shop drawings with levels, setting-out, framing, joints and every MEP opening | Consultant approval |
| 3. Samples and mock-up | Finish and brand preferences, if any | Material samples and a built mock-up area | Sign-off of the sample standard |
| 4. Installation | Access to released zones, site services | Installation to the approved drawings, zone by zone, with progress reports | Area inspections |
| 5. Snagging and handover | Your snag list | Snags closed, areas handed over | Handover sign-off |
- 01/05
How do you price a ceiling package?
- 02/05
Why shop drawings come before material
- 03/05
What is a ceiling mock-up and why do hotels insist on one?
- 04/05
How installation runs on site
- 05/05
How handover works
02
How do you price a ceiling package?
We price your BOQ line by line against the drawings. Where the BOQ and drawings disagree, or a description leaves room for two readings, we list it as a clarification instead of guessing. You get the quotation, the clarifications and the assumptions together, so your QS can compare us fairly with other bidders.
- Reflected ceiling plans and sections, with levels
- Partition layouts with the fire rating of each wall
- The specification, or the board and grid brands you expect
- The target programme and site location
No BOQ yet? Send the drawings and we will prepare the quantities.
03
Why shop drawings come before material
Shop drawings are where a ceiling package is won or lost. Ours fix the ceiling levels, the setting-out, the framing, the joints and the position of every light fitting, diffuser, sprinkler, speaker and access panel. Clashes get solved on the drawing with your MEP coordinator, before anyone orders a board.
04
What is a ceiling mock-up and why do hotels insist on one?
A mock-up is a finished sample area, often one guest room, built before the main installation starts. The client, the designer and the operator approve it, and from then on it is the standard every other room is checked against. On a hotel with hundreds of keys, or a compound with hundreds of units, it is the cheapest way to make sure the last room matches the first.
05
How installation runs on site
Our crews install to the approved shop drawings, zone by zone, in the sequence your programme releases. Framing goes in first and is checked against levels before boarding. Boards, tiles or strips follow, then jointing and finishing, then cornices and decorative work.
06
How handover works
Before handover we walk each area with your team and record every snag. We close them, walk again and hand over the area. On phased projects this happens floor by floor or building by building, so finished areas can pass to the next trade.
07FAQ
Process questions
It depends on the area, how complex the ceilings are and how many zones can be released at once. We send a proposed installation programme with the quotation and align it with your master programme after award.
FUTURE can start on released zones before every drawing is final. We can produce shop drawings and start installation zone by zone while later areas are still in design, as long as each zone we build has approved drawings.
Your consultant or designer approves them, through the main contractor where there is one. We do not order material for an area until its drawings are approved.
Start at stage one
Send your BOQ and drawings. We will come back with a quotation, the clarifications and a proposed programme.