Short answer
A ceiling package BOQ should split the work by system and by area, and state the board type, ceiling height, special details, access panels, partitions with their fire ratings, cornices, and the drawings, samples and mock-up that go with them. Send it with the reflected ceiling plans, sections, partition layouts and specification. A BOQ built that way gets quotations you can compare line by line.
FUTURE prices ceiling and partition BOQs for main contractors, developers and hotel owners, and has delivered seven hotel and resort packages between 2019 and 2025. The gaps listed below are the ones that most often turn a tender into a round of clarifications.
What should a ceiling package BOQ include?
Group the BOQ into sections that match how the work is built. The table shows the usual sections, items and units.
| Section | Items to list | Usual unit | Notes |
|---|---|---|---|
| Gypsum board ceilings | Flat ceilings by board type (standard, moisture-resistant, fire-rated) and by area | m² | State slab-to-ceiling height per area |
| Gypsum details | Coves, bulkheads, steps, curtain pelmets, curved sections | Linear metre | Measure separately from the flat area |
| Access panels | Panels by size and type (standard, moisture-resistant, fire-rated) | Number | Match the MEP drawings |
| Tile ceilings | Grid and tile by type and module | m² | Name the tile face and edge |
| Metal strip ceilings | Strip type, width, joint and finish | m² | State coastal-grade coating where needed |
| Partitions | Each wall type with its fire rating, height and build-up | m² | Note slab-to-slab walls |
| Cement board | Partitions and claddings by type | m² | State the location (wet area, impact zone) |
| Cornices and mouldings | Each profile; corners and returns; feature panels | Linear metre / number | Attach profile drawings |
| Design and approvals | Shop drawings, samples, mock-up room | Item | Price them, so nobody skips them |
| Preliminaries | Scaffold and towers, protection, cleaning, storage | Item | Say who provides each |
Which drawings and specifications should you send with the BOQ?
Send everything the BOQ refers to, in its latest revision:
- Reflected ceiling plans with levels for every area
- Ceiling sections and details for coves, steps and bulkheads
- Partition layouts showing the fire rating of each wall type
- The specification, or the systems and brands you expect, with "or approved equal" rules
- MEP layouts that show lights, diffusers, sprinklers and speakers, if they exist
- The finishes schedule, including paint
- Site location, target programme and the order in which zones will be released
FUTURE accepts BOQs in Excel or PDF and drawings in PDF or DWG through the quotation form, or a shared link for large sets.
What are the most common gaps in ceiling BOQs?
These ten gaps cause most clarifications and most price differences between bidders:
- One rate for all gypsum board, with no board type per area
- No slab-to-ceiling height, so framing depth is a guess
- Coves and bulkheads folded into the square-metre rate
- Access panels missing, or counted without sizes
- Partitions listed without fire rating, height or build-up
- Wet areas not marked, so standard board gets priced in bathrooms
- MEP drawings missing, so openings cannot be counted
- Shop drawings, samples and the mock-up left out as items
- Scaffold, protection and cleaning not assigned to anyone
- "Or equal" accepted for rated systems without asking for test evidence
How should one gypsum board ceiling item be written?
A good BOQ item tells every bidder the same thing, so nobody prices a different ceiling. For a flat gypsum board ceiling, the item should state:
- The area or room type it covers, such as "guest room bathrooms, typical floors"
- The board type and thickness, and the number of layers
- The framing system, named by brand or as the manufacturer's system "or approved equal"
- The slab-to-ceiling height range
- The jointing and finish level, and whether paint is included
- Inclusions such as perimeter trims and shadow gaps
- The unit and the measurement rule
A written example: "Supply and install suspended ceiling of moisture-resistant gypsum board, single layer, on galvanised steel framing to the manufacturer's system, slab-to-ceiling height as shown on the sections, joints taped and finished ready for paint, including perimeter trims. Location: guest room bathrooms, typical floors. Measured net in square metres." An item written like this leaves only the price to compare.
How should the quantities be measured?
State the measurement rules at the top of the BOQ: whether areas are net or gross, how openings are treated, and how details such as coves are measured. When every bidder measures the same way, price differences show real differences in method and material instead of different arithmetic.
What if you only have drawings and no BOQ?
Send the drawings anyway. FUTURE can take off the quantities and return them with the quotation, so your QS can check them against the design.
What happens after you send the BOQ to FUTURE?
- FUTURE confirms receipt and checks that the drawings needed for pricing are there.
- FUTURE prices every line against the drawings and writes down any clarification or assumption.
- You receive the itemised quotation, the clarifications and a proposed installation programme by email.
Frequently asked questions
That depends on your tender format. FUTURE prices supply and installation together by default and can split materials and labour if the BOQ asks for it.
FUTURE accepts BOQs in Excel or PDF. An editable Excel file is easier to price against and return with item references intact.
MEP drawings let the contractor count light openings, diffusers and access panels instead of guessing them. Without them, the quotation will carry an assumption for openings that may change later.
A single rate per square metre is fine for an early budget, but not for a tender. It hides board type, details and openings. See what drives the cost of a gypsum ceiling package.